Earned Value (EV) - Deepstash

Earned Value (EV)

To report the accomplishments of the project, you must apply Earned Value (EV) to the figures and calculations in the project. EV is the quantification of the “worth” of the work done to date.

In other words, EV tells you, in physical terms, what the project has accomplished. As with PV and AC, EV can be presented in a Cumulative and Current fashion.

  • Cumulative EV is the sum of the budget for the activities accomplished to date.
  • Current EV is the sum of the budget for the activities accomplished in a given period. Earned Value is also called Budgeted Cost of Work Performed (BCWP).

18

76 reads

CURATED FROM

IDEAS CURATED BY

dennisanthony

Self Motivated, Trauma Neutralizer, Lover of Persiflage & Communication!

Interested in being a certified PMP Project Manager? Follow me for curated information pertaining to the PMP certification.

Similar ideas to Earned Value (EV)

Procrastination and subjective value

Our choice to work on a project is guided by how much we value finishing that project in that moment. Psychologists call this "subjective value."

Procrastination, psychologically speaking, is what happens when the value of doing something else outweighs the value of workin...

4. Do Deep Work / Avoid Half-Work or Shallow Work

4. Do Deep Work / Avoid Half-Work or Shallow Work

Deep work is a term developed by Cal Newport, stating that all intellectual activities should be performed in a state of distraction-free concentration that pushes your cognitive capabilities to their limit.

On the other side deep work is “half-work” or “shallow work”. That...

The value of strategic side gigs

A survey of 122 senior executives from a variety of industries agreed that outside engagements were critical to leadership success now and in the future.

Meaningful engagement should be in activities that expose you to different people, information, and cultures, but is synergisti...

Read & Learn

20x Faster

without
deepstash

with
deepstash

with

deepstash

Personalized microlearning

100+ Learning Journeys

Access to 200,000+ ideas

Access to the mobile app

Unlimited idea saving

Unlimited history

Unlimited listening to ideas

Downloading & offline access

Supercharge your mind with one idea per day

Enter your email and spend 1 minute every day to learn something new.

Email

I agree to receive email updates