The Critical Chain model introduces Feed Buffers for the noncritical chain. Feed buffers are not included in the overall Project Buffer but are used as a way of insulating the critical path of the project from non-critical workstream elements. By building in Feed Buffers, CCPM reduces the risk of projects overrunning due to dependencies.